Upgrading Your Server 9-17
5. Power on the server, and run the SETUP utility.
This is because, when a hard disk drive is added, the previously recorded boot order
settings are cleared.
6. Install the front bezel you removed in step 2.
2.5-inch hard disk drive
IMPORTANT:
Do not press the POWER switch during the
installation or removal of the hard disk drive if your server is running.
1. See page 9-4 to prepare.
2. Push the lever to unlock,
DISK LED